Thursday, February 12, 2009

Tuesday, February 10, 2009

End of day five.



The remaining exposed wall are now covered and patching has begun.

Monday, February 9, 2009

End of Fourth day.



The Electrical and plumbing prep work is now complete. The window's edge is reinforce and clean up. The old vent to the range hood is torn down, and is replaced.

End of third day



New Window is now in place, and the electrical prep work has started.

End of second day.




If you ever wonder why the kitchen is so short, look at the three layers of vinyl floors.

End of first day demolition.


1st day, predemolition pictures.